Court rules that corona crisis does not constitute force majeure – dated April 10, 2020 – mr. AW Dolphin
If payment cannot be made due to the loss of income, then
there is not always a force majeure situation. The Court of Den Bosch 23
March 2020 (ECLI:NL:RBOBR:2020:1763) ruled that a tenant cannot appeal
to force majeure because of the corona crisis, because from the
commencement of the lease and therefore before the corona crisis
late payment of rent. The backlog was possible with the corona crisis
not be logged in. The lessor claimed the entire arrears,
plus fines for late payment. The court held as follows:
“As far as[gedaagden] intended to appeal with their defence
financial inability or inability to pay, the inability to pay,
no matter how annoying[gedaagden] , in the risk sphere of[gedaagden] is
and not release them from their payment obligations under the
lease agreement[eisers] dismisses. The subdistrict court judge signs this
indicates that it is already too late from the start of the rental agreement
payments through[gedaagden] , while there was no corona at that time
crisis.”
The court rules that the claimed entire rent arrears and fine
will have to be paid.
Perhaps the judgment would have been different if there had been no question at all
was from a late payment prior to the corona crisis and the
payment arrears are wholly and exclusively attributable to the
corona crisis.
mr. AW Dolphijn – franchise lawyer
Ludwig & Van Dam Franchise attorneys, franchise legal advice. Want
you respond? Go to dolphijn@ludwigvandam.nl

Other messages
Interests Association of Franchisees of the Netherlands (BVFN) is in further consultation with the Minister
On April 16, 2014, the previously announced meeting between the Belangen Vereniging Franchisenemers Nederland (BVFN) and the Ministry of Economic Affairs took place.
Exoneration of duty of care with the franchisor’s prognosis
In a judgment of the Overijssel court of 9 April 2014, the interesting question arose whether a collaboration should be qualified as a franchise.
Non-competition clause is lost in summary proceedings
Recently, the preliminary relief judge in Rotterdam ruled that a franchisee was not bound by the non-competition clause included in the franchise agreement.
Advance on compensation after an unsound prognosis
In a beautifully substantiated summary judgment of the Northern Netherlands Court of 9 April 2014, the question was whether an advance should be paid for the damage assessment procedure.
Collection point requires shopping destination
In my supermarket newsletter of July 11, 2013, I already predicted that the establishment of collection points for goods ordered via the internet would set the judicial pens in motion.
Developments and sales via the internet.
Developments and sales via the internet.